| Professional Registrations
Florida Licensed General Contractor
FDOT Asphalt Inspector
ACI Level II Concrete Inspector
Responsibilities for TSG
Mr. Standridge, TSG's Vice President of Construction,
is a senior construction manager (CM) with experience in construction
management and construction services since 1976. He is a licensed
general contractor with experience in management or supervisory roles.
He directs TSG's construction group and has managed such constructions
projects as the Burnt Store, Ritz-Carlton, Sapphire Beach, Westin St.
John, Kiawah ASR and Royal St. Kitts 1 MGD desalination plant on behalf
of TSG. As well as having extensive experience in fast-track and alternative
project delivery, he specializes in management of multi-phase heavy
construction projects, including water and wastewater treatment plants;
conventional, brackish and seawater treatment plants and groundwater
systems; pipelines; airports; roads, bridges, elevated highways, and
subways; and public utility facilities. Mr. Standridge also specializes
in concrete and coatings applications. Mr. Standridge's responsibilities
include working with consultants as part of their design team to provide
field feedback to the design staff. He provides such services as
constructability reviews of design phase projects, construction cost estimates,
construction scheduling, budgets for services during construction (SDC),
quality control (QC) review, and construction management services throughout
the design and construction phases. Mr. Standridge works in the company's
engineering and fabrication facility in Gainesville, Florida.
Experience
Mr. Standridge was the CM for the Gasparilla WWTP design/build
project. This project included a fast-track installation
of a 0.5-million-gallon-per-day (mgd) package plant at an
existing golf course in Boca Grande, Florida. The design/build
approach facilitated the 6-month construction window available
during the golf course’s off-season. During this 6-month
window, an existing circular package plant was removed and
replaced by a larger, deeper package plant and an existing
concrete package plant was rehabilitated. Construction activities
were complicated by the requirement to continue processing
wastewater at the existing facility, the tidally impacted
surficial groundwater, and an extremely tight construction
site. Mr. Standridge has also recently completed other design/build
projects in central Florida.
For the City of Tampa’s Water Quality 2000 project,
Mr. Standridge was the CM. This project included mechanical,
electrical, and automation improvements for the Hillsborough
River and Morris Bridge Water Treatment Plants and associated
re-pump stations.
For the Summerville Commissioners of Public Works in South
Carolina, Mr. Standridge served as CM and resident observer
for the 2-year, 10-mgd wastewater treatment plant (WWTP)
expansion project. The new plant included carrousel biological
nutrient removal basins, sludge handling and load-out facilities,
effluent storage basins, a pumping station, an administration
building, and a remote post aeration facility. His responsibilities
included overall project management, review of project schedules,
coordination of shop drawings and request for information
(RFI) responses, initiation of change orders, and oversight
of inspection personnel.
Mr. Standridge was CM for the Reedy Creek Improvement District
wastewater treatment and reclaimed water system upgrade
in Orlando, Florida. This 3-year, fast-track program consisted
of a WWTP expansion, rapid infiltration basin, composting
facilities, material recycling facility, reuse water distribution
system, and administrative facilities. His responsibilities
included reviewing project schedules, initiating change
orders, reviewing and coordinating shop drawings and responses
to RFIs, and overall management of inspection personnel
and testing laboratories.
Mr. Standridge was the CM on two well projects for the Englewood
Water District, Florida. The first project consisted of
drilling twelve 12-inch-diameter groundwater production
well pumps and a 16-inch transmission main to supply an
existing lime softening WTP. The second project included
testing and developing two 12-inch reverse osmosis (RO)
production wells and one 6-inch monitoring well.
Also for the Englewood Water District, Mr. Standridge was
CM for an RO treatment plant and supply wells, and four
major water transmission mains, a meter repair building,
and an office building addition.
For Pasco County, Florida, Mr. Standridge was CM for a project
that featured the construction of two regional treatment
plants, one of which was 3.0 mgd and the other 3.5 mgd.
His responsibilities included overall management of inspection
personnel and coordination of construction activities of
multiple prime contractors. Mr. Standridge assisted in shop
drawing review, change order administration, testing laboratory
coordination, and other SDC.
Mr. Standridge was also the lead resident observer for a
multimillion-dollar, two-phase Hillsborough County Aviation
Authority Airport Expansion Airside "F" project.
This project involved constructing concrete runways, aprons,
taxiways, underground fueling systems, and storm water runoff
facilities with outfall structures. He was responsible for
the overall management of inspection personnel and the coordination
of construction activities of multiple prime contractors.
He assisted in shop drawing review, change order administration,
testing laboratory coordination, and other SDC.
Mr. Standridge was resident observer for two wastewater
injection wells, a pumping station, and transmission mains
for the City of St. Petersburg, Florida. The wells and pumping
station were constructed at the City's Southeast WWTP. The
54-inch to 24-inch-diameter telescoping injection wells
were constructed to a depth of 2,000 feet.
Other projects for the City of St. Petersburg for which
Mr. Standridge served as resident observer include four
sludge-dewatering facilities, a 5.0-mgd storage tank and
pumping station, and two injection wells.
Mr. Standridge served as resident observer for an award-winning
alum sludge-dewatering project at the Hillsborough River
WTP in Tampa, Florida. This project included the construction
of two large sludge thickeners and a two-story sludge dewatering
facility housing six 2-meter belt presses, polymer mixing
and feed systems, and a sludge loading station.
|